A supplier misses delivery, a tenant pays rent late, a contractor stops work half-way. Can the other side terminate for every delay, or must it first give more time? A mistaken termination notice can turn the terminating party into the party in breach. This article starts from the Majalla’s option of condition (khiyar al-shart) and mutual rescission (iqala), then covers default and termination under the Turkish Code of Obligations, the English law of repudiatory breach, and published ICC awards on fundamental breach under the CISG.
The Majalla: option of condition and mutual rescission
The Majalla regulates the khiyar al-shart, an option allowing a party to undo a contract within an agreed period. According to secondary accounts, Article 300 provides that a condition may be attached to the contract. The option exists only in contracts capable of being rescinded. Classical law therefore tied a party’s power to undo a contract either to a right agreed in advance or to mutual consent (iqala).
Under modern Turkish law, the right to withdraw arises in cases listed by statute, such as the debtor’s default. What the Majalla contributes here is the idea that a power to undo a contract needs a clear basis. (The article number for iqala could not be verified and is therefore not given.)
Turkish law: default, extra time and withdrawal
- Extra time (TCO Art. 123): in a bilateral contract, if one party is in default, the other may give a reasonable period for performance or ask the court to set one. The period is the additional time granted to the debtor before the creditor may exercise its options.
- No need for extra time (TCO Art. 124): where granting time would be useless because of the debtor’s attitude, where a fixed date was agreed, or where the debtor has declared it will not perform, the creditor may use its options without granting time. Outside these cases, withdrawal without having granted time is risky; reported Court of Cassation decisions have treated termination without a grace period as unjustified.
- Options (TCO Art. 125): once the period has expired without performance, the creditor may (1) claim performance and damages for delay, (2) waive performance and claim damages for non-performance (positive interest), or (3) withdraw from the contract. On withdrawal, the parties are released from their obligations and may reclaim what they have already performed (Art. 125/3).
- Continuing contracts: in leases, services and other continuing obligations, termination with effect for the future applies instead of withdrawal, and past performance is not returned.
Disputes in practice centre on three points: whether default has actually occurred, whether granting extra time was necessary, and whether the withdrawal notice was given in time and in the form the contract requires. For delay and delay penalties, see also our article on construction delay.
The English law view: repudiatory breach and termination
Under English law, not every breach gives a right to terminate. The right depends on the nature of the term broken and the consequences of the breach. A party may terminate for breach of a condition, or for a breach that deprives the other party of substantially the whole benefit it was intended to receive under the contract (a repudiatory breach).
- Hochster v De La Tour (1853) 2 E&B 678: where a party repudiates the contract before the date for performance, the other may sue for damages at once without waiting for that date (anticipatory breach). Performance was due to start on 1 June; the repudiation was sent on 11 May.
- Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26: the Court of Appeal held that some terms are neither conditions nor warranties (innominate terms), and that whether a breach allows termination depends on its consequences, namely whether the innocent party is deprived of substantially the whole benefit of the contract.
- Grand China Logistics Holding (Group) Co Ltd v Spar Shipping AS [2016] EWCA Civ 982: the Court of Appeal held that failure to pay an instalment of charter hire punctually did not in itself breach a condition. Whether late payment justifies termination depends on construction of the contract and the seriousness of the breach.
Comparison: Turkish law ties withdrawal mainly to default and the extra period granted, while English law looks at the nature of the term and the seriousness of the breach. In both systems, a wrongful termination may make the terminating party the one in breach. The termination clauses of the contract and the characterisation of the breach should therefore be assessed with care before a notice is sent.
Examples from arbitration: fundamental breach under the CISG
CISG Art. 25 treats a breach as fundamental if it substantially deprives the other party of what it was entitled to expect under the contract, and Art. 49 gives the buyer the right to avoid the contract in that case. Published ICC awards include:
- ICC Case 7531 (1994): the tribunal treated the non-conformity of an important part of the goods supplied as a fundamental breach under Art. 25 and did not allow the seller to cure by supplying substitute goods. CISG-online’s commentary notes that the award is read as placing the right to avoid above the seller’s right to cure, which remains contested.
- ICC Case 9978 (1999): the tribunal held that non-delivery was a fundamental breach and that the buyer could avoid the contract under Art. 49(1)(a).
- ICC Bulletin award (2000): the tribunal said that fundamental breach should be interpreted narrowly, but held that refusal to pay the price was a fundamental breach.
These awards show that what matters is not delay in the abstract but how much of the benefit the other party expected has been lost. Before terminating, the nature of the breach, whether extra time was granted and any special terms of the contract should be assessed together.
Frequently asked questions
Can I withdraw for any delay? No. As a rule default is required and a reasonable extra period must be granted (TCO Art. 123). Art. 124 separately covers cases where granting time is useless or a fixed date applies.
I withdrew without granting time; have I made a mistake? Unless a case under Art. 124 applies, the withdrawal may be treated as unlawful and may work against the party that withdrew. The facts are decisive.
Is withdrawal the same as termination? No. Withdrawal in one-off contracts operates retroactively and performance is returned. In continuing contracts, termination operates only for the future.
Does English law apply to my contract? No; the governing law is fixed separately. This section is for comparison.
For general information only; not legal advice. The right to withdraw or terminate and its consequences depend on the contract and the facts. Sources: Majalla Art. 300 (as reported in secondary sources); Turkish Code of Obligations Arts. 123, 124, 125; Hochster v De La Tour (1853) 2 E&B 678; Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26; Grand China Logistics Holding (Group) Co Ltd v Spar Shipping AS [2016] EWCA Civ 982; CISG Arts. 25, 49; ICC Case 7531 (1994), ICC Case 9978 (1999) and an ICC Bulletin award (2000) (as summarised on Unilex and CISG-online).