PGN v CRW: must a disputed DAB decision be paid?

Every contractor working under FIDIC knows the problem: the Dispute Adjudication Board (DAB) orders the employer to pay, the employer serves a notice of dissatisfaction and does not pay. In this decision the Singapore Court of Appeal accepted that even a DAB decision that has been challenged and is not yet final can be enforced through an interim arbitral award.

Case details

  • Case: PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30
  • Court: Singapore Court of Appeal; majority (Sundaresh Menon CJ and Quentin Loh J; Chan Sek Keong SJ dissenting)
  • Date: 27 May 2015
  • Arbitration: ICC Case No. 18272/CYK; interim award of 22 May 2013 (majority), USD 17,298,834.57
  • Contract: pipeline contract based on the 1999 FIDIC Red Book, governed by Indonesian law (South Sumatra-West Java gas pipeline)
  • Earlier round: the final award in the first arbitration had been set aside by the Singapore courts ([2010] 4 SLR 672; Court of Appeal, 13 July 2011, [2011] 4 SLR 305)

The ruling in one sentence: clause 20.4 of the 1999 FIDIC Red Book obliges the parties to give prompt effect to a DAB decision even if they dispute it; a breach of that obligation can be referred directly to arbitration, and an interim award can be made for the unpaid sum while the underlying dispute continues.

What was the dispute?

In 2006 PGN, Indonesia’s gas transmission company, engaged CRW, a joint operation of three Indonesian companies, to design, procure, install and test a gas pipeline from South Sumatra to West Java. In a dispute over variation orders, the DAB decided that PGN should pay CRW about USD 17.3 million. PGN served a notice of dissatisfaction (NOD) and did not pay. The final award CRW obtained in a first arbitration in 2009 was set aside by the Singapore courts because the tribunal had turned the DAB decision into a final award without examining its merits. In 2011 CRW started a second arbitration, asking for a final resolution of the underlying dispute and, in the meantime, an interim award for the DAB sum. The majority of the tribunal made the interim award; PGN applied to set it aside.

Key passages

“One point that seems to have attracted almost universal acceptance in this case, save of course on the part of PGN, is that cl 20.4 (specifically, cl 20.4[4]) evinces a clear intention for parties to promptly comply with a DAB decision, irrespective of any disagreement or dissatisfaction with it. This serves the vital objective of safeguarding cash flow in the building and construction industry, especially that of the contractor, who is usually the receiving party.”

Para. 71

“In our judgment, cl 20.4 is aimed at addressing precisely these concerns, and cl 20 should therefore be interpreted in a manner which promotes prompt compliance with a DAB decision …”

Para. 75

The majority departed from the court’s own 2011 view (that all issues should be resolved together in a single arbitration) and accepted that a breach of the payment obligation can be the subject of a separate arbitration, or of a separate interim award in the same arbitration (para. 83). Because the interim award would not be varied by the later final award on the underlying dispute, it found no conflict with s.19B of Singapore’s International Arbitration Act. PGN’s appeals were dismissed.

Why it matters

  • “Pay now, argue later”: in Singapore-seated arbitrations, failure to pay a challenged DAB decision can be pursued as a claim in its own right; the receiving party need not wait for the outcome of the underlying dispute.
  • How the claim is framed: CRW succeeded by framing its case as two separate questions: whether the DAB sum is ultimately owed, and whether the contract requires it to be paid now.
  • The edition matters: later FIDIC editions reworked the provisions on failure to comply with DAB decisions. Which edition and which amendments apply must be checked on each project.

The view from Türkiye

Turkish contractors frequently work abroad under FIDIC contracts, especially on projects backed by international financial institutions. Turkish law has no statutory adjudication scheme for construction disputes, so the binding effect of a DAB decision rests largely on the contract wording and on the law of the seat. On projects governed by Turkish law or seated in Türkiye, stating expressly in the contract which route applies if a DAB decision is not complied with (a separate arbitration, an interim award, interim measures) can avoid a dispute running for years, as it did in PGN.

Frequently asked questions

I have served a notice of dissatisfaction. Do I still have to pay? Under clause 20.4 of the 1999 FIDIC Red Book, the decision is binding until revised by amicable settlement or an arbitral award, and must be given prompt effect. PGN confirmed that a notice of dissatisfaction does not suspend the payment obligation.

Can money paid under an interim award be recovered later? Yes. If the final award on the underlying dispute differs from the DAB decision, the account between the parties is adjusted accordingly. The interim award protects cash flow until the final resolution.

For general information only; not legal advice. Sources: PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30, paragraphs 1, 3-15, 71, 75, 83, 111 (elitigation.sg); CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] 4 SLR 305; PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2010] 4 SLR 672; 1999 FIDIC Red Book, cl 20.4-20.7; Singapore International Arbitration Act, s.19B.